Interstate-94 Resurfacing & Noise Wall Project
Noise Wall materials presented at meetings, but may not yet be on MN DOT website
July 31 2018 community meeting materials
September 19 2018 community meeting materials
December 4 2018 community meeting materials
This page was last updated on: February 15, 2019
Number of visitors since December 26, 2018
Attention:
If you would like to voice your opinion on the subject and encourage your City Council to vote on this item, please plan to attend this meeting!
Attention:
As of Friday, January 25, a survey to Rice Lake Area residents was completed seeking input on the Noise Wall #1 project (from Weaver Lake Road to the 1st bridge). Results of that survey can be found in these documents:
This data was sent to the City of Maple Grove to the attention of the City Council members to assist them when they vote on the project.
Looking ahead, there will be another Public Meeting on Tuesday, January 29 from 6-8:00 pm at the Maple Grove Government Center (Emergency Operations Center) for an update on this project.
Attention:
As of Monday, February 4, the Maple Grove City Council recommended approving Noise Wall #1 by a vote of 4 to 1. The vote will be submitted by the Public Works department. View the February 4th City Council meeting at:
Attention:
As of Friday, February 15, MN DOT recognizes that Noise Wall #1 has been approved by enough votes. The other 3 walls up for voting also appear to have enough to be approved at this time.
Wall NB1
East side of I-94 between Weaver Lake Rd. and Trail Bridge in Maple Grove
Total eligible points: 96
Yes Points: 90 (94%)
No Points: 1 (1%)
Decision: Wall will be constructed
Wall NB3
East side of I-94 between Trail Bridge and 93rd Ave. N. in Maple Grove
Total eligible points: 192
Yes Points: 68 (35%)
No Points: 12 (6%)
Decision: To be determined
Wall NB12
West side of I-94 between Weaver Lake Rd. and Wedgewood Way N. in Maple Grove
Total eligible points: 351
Yes Points: 140 (40%)
No Points: 33 (9%)
Decision: To be determined
Wall NB13
West side of I-94 between Wedgewood Way N and 73rd Ave. N. in Maple Grove
Total eligible points: 156
Yes Points: 103 (66%)
No Points: 0 (0%)
Decision: Wall will be constructed
Map of proposed Noise Walls in Maple Grove
Voting Tally (as of Feb. 15, 2019)